The new Incline Beach House has cleared its foundation phase, and IVGID's latest update points to sidewalks, building enclosure and winterizing the site as the next steps.
Construction progress so far
IVGID's Incline Beach House Project page lists five completed milestones since demolition wrapped in early June.
Milestone | Completed |
|---|---|
Demolition and re-grading | Early June 2026 |
Deep underground utilities and vault install | End of June 2026 |
Footings and stem walls | Mid-July 2026 |
Plumbing and electrical below slab | Early August 2026 |
Foundation pour | Complete |
The same update lists finishing the underground utilities and paving alongside the completed items. IVGID's site logistics map shows the construction zone and the modified parking areas.
What's being built and what comes next
The project replaces the 60-year-old snack bar with a food service building that includes a commercial kitchen, a bar, patio seating and fire pits, according to IVGID's summer 2026 guide to Incline Beach. The restrooms are expanding and will operate year-round, which removes the need for temporary porta-potties outside holiday periods.
IVGID General Manager Robert Harrison said, "It's been a long road to get to this point." KUNR's coverage notes the project replaces facilities more than 60 years old.
Next on IVGID's list are pouring sidewalks, enclosing the building and winterizing the site. As of March 2026, IVGID scheduled completion for mid-summer 2027, so construction impacts continue into the 2027 beach season.
Renderings and design
IVGID has released renderings of the new building. The patio rendering shows the beach house and patio, and the stage rendering shows the upgraded band area. The full plans are in the architectural design development drawings and the materials study, both dated June 2025.
Per IVGID, the design aims to blend into the natural setting and keep the Lake Tahoe views intact. The bar moves slightly closer to the lake, with separate queues for the bar and the food window. Two new fire pits sit just west of the patio.
IVGID's food and beverage manager describes tropical-inspired, citrus-forward flavors and sunset cocktails. The venue is meant to be family-friendly by day and a relaxed lounge by evening.
How we got here
In January 2022, IVGID's Community Services Master Plan called the beach house a "top tier recommendation," per the district's project page. Dates below come from that page and IVGID's summer 2026 guide unless noted.
Date | Milestone |
|---|---|
Early June 2026 | Demolition and re-grading completed |
Mid-April 2026 | Construction set to begin, per KUNR |
Feb. 26, 2026 | Final permitting in process with Washoe County and TRPA |
Dec. 10, 2025 | Board approves the final construction contract with CORE Construction |
Oct. 2-23, 2025 | Construction bidding open |
Sept. 19, 2025 | Permits submitted to TRPA |
Sept. 17, 2025 | Trustees reaffirm support for select added alternates |
June 24, 2025 | CORE submits design development drawings |
Jan. 29, 2025 | Public Works presents the project's history to the Board |
2023 | Request for qualifications drew four design-build teams; three were shortlisted and CORE was chosen |
Jan. 2022 | Board confirms the beach house as a priority project |
2016 | Trustees begin prioritizing replacement of the outdated restrooms and snack bar |
What to expect if you visit
These details come from IVGID's May 2026 guide, so confirm current conditions on IVGID's beach page.
Area | During construction |
|---|---|
Beach and shore zone | Open |
Picnic tables, Third Creek field, playground | Open (most picnic tables under the trees) |
Usual vehicle and pedestrian entrance | Closed; temporary entrance to the west, near Village Blvd. |
Parking | Limited by fencing; Aspen Grove and Overflow lots across Lakeshore Blvd. suggested |
Who can visit | IVGID Pass holders and their guests |
Food and beverage | Moved to Ski Beach |
Music on the Beach and beach food
Music on the Beach moved to Ski Beach for 2026. IVGID now manages the series and contracted Mitch Harbaugh, who has run the concerts for more than 15 years, to book the bands and emcee.
Food and beverage service moved to Ski Beach during construction. The upgraded band infrastructure is meant to bring the concerts back to Incline Beach for the 2027 season.
How to follow along
IVGID posts progress on its Incline Beach House Project page and lists other district work on its major capital improvement project updates page. IVGID's site also offers a signup for news and event updates.
What it means for Incline Village owners and buyers
For homeowners, the project replaces facilities more than 60 years old with year-round restrooms, a commercial kitchen and a patio. IVGID says the work is funded by Facility Fees it has already collected, and IVGID Pass holders keep beach access during construction.
For buyers, the open question is timing. IVGID's March 2026 schedule puts completion in mid-summer 2027, and the district says construction impacts continue into the 2027 beach season. Ask us for IVGID's latest update before you tour.
For sellers listing before the project finishes, be ready to explain the temporary entrance, limited parking and Ski Beach food service. We can share IVGID's beach page and project updates so buyers get accurate information.
Thinking about buying or selling in Incline Village? Visit Lakeshore Realty or stop by 954 Lakeshore Blvd.
Lakeshore Realty - B.04440
Frequently asked questions
When will the Incline Beach House be finished?
As of March 2026, IVGID scheduled completion for mid-summer 2027. Its latest update lists the foundation pour as complete, with sidewalks, building enclosure and winterizing next.
How much does the Incline Beach House cost?
IVGID's budget is $11 million, collected through Facility Fees. The forecast cost is $10,992,280, covering pre-construction, construction and district staff time, per IVGID's summer 2026 guide.
Who is building the Incline Beach House?
CORE Construction is the design-build team and project construction manager, and the Board approved the final construction contract on December 10, 2025. A March 2025 Board memo recommended a $755,000 agreement with CORE for construction development documents.
What will the new Incline Beach House include?
It includes a commercial kitchen, ordering and pick-up windows, a bar, patio seating, fire pits and expanded year-round restrooms, per IVGID's summer 2026 guide. The project also improves the vehicle turn-around and drop-off areas and upgrades the band infrastructure.
Sources
- IVGID: Incline Beach House Project (published Oct 1, 2026; update dated Aug 20, 2026)
- IVGID: What To Expect At Incline Beach This Summer & Next (May 20, 2026)
- KUNR: Big changes ahead at Incline Beach as $11M project gets underway (April 10, 2026)
- IVGID Board memo, Item G.2, March 12, 2025