Incline Beach House Update: What's Been Built and What's Next

Incline Beach House Update: What's Been Built and What's Next

The new Incline Beach House has cleared its foundation phase, and IVGID's latest update points to sidewalks, building enclosure and winterizing the site as the next steps.

Construction progress so far

IVGID's Incline Beach House Project page lists five completed milestones since demolition wrapped in early June.

Milestone

Completed

Demolition and re-grading

Early June 2026

Deep underground utilities and vault install

End of June 2026

Footings and stem walls

Mid-July 2026

Plumbing and electrical below slab

Early August 2026

Foundation pour

Complete

The same update lists finishing the underground utilities and paving alongside the completed items. IVGID's site logistics map shows the construction zone and the modified parking areas.

What's being built and what comes next

The project replaces the 60-year-old snack bar with a food service building that includes a commercial kitchen, a bar, patio seating and fire pits, according to IVGID's summer 2026 guide to Incline Beach. The restrooms are expanding and will operate year-round, which removes the need for temporary porta-potties outside holiday periods.

IVGID General Manager Robert Harrison said, "It's been a long road to get to this point." KUNR's coverage notes the project replaces facilities more than 60 years old.

Next on IVGID's list are pouring sidewalks, enclosing the building and winterizing the site. As of March 2026, IVGID scheduled completion for mid-summer 2027, so construction impacts continue into the 2027 beach season.

Renderings and design

IVGID has released renderings of the new building. The patio rendering shows the beach house and patio, and the stage rendering shows the upgraded band area. The full plans are in the architectural design development drawings and the materials study, both dated June 2025.

Per IVGID, the design aims to blend into the natural setting and keep the Lake Tahoe views intact. The bar moves slightly closer to the lake, with separate queues for the bar and the food window. Two new fire pits sit just west of the patio.

IVGID's food and beverage manager describes tropical-inspired, citrus-forward flavors and sunset cocktails. The venue is meant to be family-friendly by day and a relaxed lounge by evening.

How we got here

In January 2022, IVGID's Community Services Master Plan called the beach house a "top tier recommendation," per the district's project page. Dates below come from that page and IVGID's summer 2026 guide unless noted.

Date

Milestone

Early June 2026

Demolition and re-grading completed

Mid-April 2026

Construction set to begin, per KUNR

Feb. 26, 2026

Final permitting in process with Washoe County and TRPA

Dec. 10, 2025

Board approves the final construction contract with CORE Construction

Oct. 2-23, 2025

Construction bidding open

Sept. 19, 2025

Permits submitted to TRPA

Sept. 17, 2025

Trustees reaffirm support for select added alternates

June 24, 2025

CORE submits design development drawings

Jan. 29, 2025

Public Works presents the project's history to the Board

2023

Request for qualifications drew four design-build teams; three were shortlisted and CORE was chosen

Jan. 2022

Board confirms the beach house as a priority project

2016

Trustees begin prioritizing replacement of the outdated restrooms and snack bar

What to expect if you visit

These details come from IVGID's May 2026 guide, so confirm current conditions on IVGID's beach page.

Area

During construction

Beach and shore zone

Open

Picnic tables, Third Creek field, playground

Open (most picnic tables under the trees)

Usual vehicle and pedestrian entrance

Closed; temporary entrance to the west, near Village Blvd.

Parking

Limited by fencing; Aspen Grove and Overflow lots across Lakeshore Blvd. suggested

Who can visit

IVGID Pass holders and their guests

Food and beverage

Moved to Ski Beach

Music on the Beach and beach food

Music on the Beach moved to Ski Beach for 2026. IVGID now manages the series and contracted Mitch Harbaugh, who has run the concerts for more than 15 years, to book the bands and emcee.

Food and beverage service moved to Ski Beach during construction. The upgraded band infrastructure is meant to bring the concerts back to Incline Beach for the 2027 season.

How to follow along

IVGID posts progress on its Incline Beach House Project page and lists other district work on its major capital improvement project updates page. IVGID's site also offers a signup for news and event updates.

What it means for Incline Village owners and buyers

For homeowners, the project replaces facilities more than 60 years old with year-round restrooms, a commercial kitchen and a patio. IVGID says the work is funded by Facility Fees it has already collected, and IVGID Pass holders keep beach access during construction.

For buyers, the open question is timing. IVGID's March 2026 schedule puts completion in mid-summer 2027, and the district says construction impacts continue into the 2027 beach season. Ask us for IVGID's latest update before you tour.

For sellers listing before the project finishes, be ready to explain the temporary entrance, limited parking and Ski Beach food service. We can share IVGID's beach page and project updates so buyers get accurate information.

Thinking about buying or selling in Incline Village? Visit Lakeshore Realty or stop by 954 Lakeshore Blvd.

Lakeshore Realty - B.04440

Frequently asked questions

When will the Incline Beach House be finished?

As of March 2026, IVGID scheduled completion for mid-summer 2027. Its latest update lists the foundation pour as complete, with sidewalks, building enclosure and winterizing next.

How much does the Incline Beach House cost?

IVGID's budget is $11 million, collected through Facility Fees. The forecast cost is $10,992,280, covering pre-construction, construction and district staff time, per IVGID's summer 2026 guide.

Who is building the Incline Beach House?

CORE Construction is the design-build team and project construction manager, and the Board approved the final construction contract on December 10, 2025. A March 2025 Board memo recommended a $755,000 agreement with CORE for construction development documents.

What will the new Incline Beach House include?

It includes a commercial kitchen, ordering and pick-up windows, a bar, patio seating, fire pits and expanded year-round restrooms, per IVGID's summer 2026 guide. The project also improves the vehicle turn-around and drop-off areas and upgrades the band infrastructure.